Campbeltown’s New Quay upgrade on schedule

new-quay-campbeltown-20_31bam02

Local workers employed by BAM Nutall and contractors working on the New Quay. 20_c31bam02

A MULTI-million pound upgrade to Campbeltown’s New Quay is on schedule to be complete by mid October.

BAM Nuttall,the Dutch-owned engineering firm awarded the project by Argyll and Bute Council,are progressing well with the work to deepen the harbour to allow larger vessels to berth.

Once the £4.6million upgrade is complete,vessels large enough to carry six-metre diameter wind turbine towers will be able to use the New Quay.

For full article see Campbeltown Courier edition of Friday August 3 2012 or on line at www.campbeltowncourier.co.uk/digital


Related Posts:

Advertising Feature

Keeping your money safe online – 5 top tips

5 ways to go green this year

Break up the winter with a luxury Caribbean cruise

Saving money on your heating bills this winter

The Way to Your Home’s Heart is Through the Kitchen


Related Posts:

Smart Youtube Widget

We want your Stories,Videos,Photos!

Send online click here
(text,photo and video)


Newsdesk 01586 554646

Campbeltown Courier
Main and Longrow South
Campbeltown
Argyll
PA28 6AE

Terms and conditions apply click here

Click Here to read the current digital edition


Scan to Get our E-Alerts

Read More »